Checklist Service Design Package SDP: Difference between revisions
mNo edit summary |
No edit summary |
||
Line 14: | Line 14: | ||
'''Source''': Checklist "Service Design Package - SDP" from the [https://en.it-processmaps.com/products/itil-process-map.html ITIL Process Map V3] | '''Source''': Checklist "Service Design Package - SDP" from the [https://en.it-processmaps.com/products/itil-process-map.html ITIL Process Map V3] | ||
<p> </p> | |||
The ''Service Design Package (SDP)'' builds upon the [[Service Level Management#SLR|Service Level Requirements]]. It further specifies the requirements from the viewpoint of the client and defines how these are actually fulfilled from a technical and organizational point of view. It is assumed that a bundle of Supporting Services is combined in order to deliver a Business Service for the client. In this context, the IT organization may opt to supply the Supporting Service with its own resources, or to use an external service supplier. | |||
The Service Design Package is passed from [[ITIL V3 Service Design|Service Design]] to the [[ITIL V3 Service Transition|Service Transition]] process and details all information required in order to develop the service solution, including a preliminary (intended) time-schedule for the Service Transition phase. | |||
<p> </p> | |||
'''The Service Design Package contains the following information (the actual level of detail will vary, depending on the type of service):''' | '''The Service Design Package contains the following information (the actual level of detail will vary, depending on the type of service):''' | ||
<p> </p> | |||
==== Service Design Package - Part 1: Header ==== | ==== Service Design Package - Part 1: Header ==== | ||
Line 31: | Line 30: | ||
# Name of the service | # Name of the service | ||
# Clearance information (with location and date) | # Clearance information (with location and date) | ||
## Clearance of the Service Design Manager | ## Clearance of the [[Roles within ITIL V3#Service Design Manager|Service Design Manager]] | ||
## Clearance of the Service Design Package by Service Management (confirmation that the requirements as laid out in this document are able to be fulfilled and where necessary, specification of any preconditions which must be fulfilled before the service can go operational) | ## Clearance of the Service Design Package by Service Management (confirmation that the requirements as laid out in this document are able to be fulfilled and where necessary, specification of any preconditions which must be fulfilled before the service can go operational) | ||
### Capacity Manager | ### [[Roles within ITIL V3#Capacity Manager|Capacity Manager]] | ||
### Availability Manager | ### [[Roles within ITIL V3#Availability Manager|Availability Manager ]] | ||
### IT Service Continuity Manager | ### [[Roles within ITIL V3#IT Service Continuity Manager|IT Service Continuity Manager]] | ||
### Security Manager | ### [[Roles within ITIL V3#Information Security Manager|Information Security Manager]] | ||
### Compliance Manager | ### [[Roles within ITIL V3#Compliance Manager|Compliance Manager]] | ||
### Financial Manager | ### [[Roles within ITIL V3#Financial Manager|Financial Manager]] | ||
<p> </p> | |||
==== Service Design Package - Part 2: Detailed Requirements Specification as a Basis for Service Transition ==== | ==== Service Design Package - Part 2: Detailed Requirements Specification as a Basis for Service Transition ==== | ||
This part builds upon the Service Level Requirements and specifies in more detail what conditions the new service and its underlying applications and infrastructure must fulfill, providing all information which is needed for building the new service. | This part builds upon the [[Service Level Management#SLR|Service Level Requirements]] and specifies in more detail what conditions the new service and its underlying applications and infrastructure must fulfill, providing all information which is needed for building the new service. | ||
# Service level requirements (reference to the [[Service Level Management#SLR|SLR]] document, where service level requirements are defined) | |||
# Service level requirements (reference to the SLR document, where service level requirements are defined) | |||
# Functional requirements (the SLR document contains a summary description of the desired customer outcome; however, functional requirements may need to be specified in greater detail, especially if new applications/ systems are to be developed) | # Functional requirements (the SLR document contains a summary description of the desired customer outcome; however, functional requirements may need to be specified in greater detail, especially if new applications/ systems are to be developed) | ||
# | # Information security requirements which are relevant for the service | ||
# Compliance requirements which are relevant for the service | # Compliance requirements which are relevant for the service | ||
# Architectural constraints (e.g. specific technology or vendors) | # Architectural constraints (e.g. specific technology or vendors) | ||
Line 57: | Line 55: | ||
# Required access rights (which users or user groups will require access to the service, and what levels of access must be provided) | # Required access rights (which users or user groups will require access to the service, and what levels of access must be provided) | ||
<p> </p> | |||
==== Service Design Package - Part 3: Technical and Organizational Implementation Blueprint ==== | ==== Service Design Package - Part 3: Technical and Organizational Implementation Blueprint ==== | ||
This part details what must be done during Service Transition to meet the specified requirements. | This part details what must be done during [[ITIL V3 Service Transition|Service Transition]] to meet the specified requirements. | ||
# Transition strategy (a brief outline of the selected approach to implementing the new service) | # Transition strategy (a brief outline of the selected approach to implementing the new service) | ||
Line 72: | Line 69: | ||
## Internal Infrastructure Services on which this service is based | ## Internal Infrastructure Services on which this service is based | ||
### Names of the infrastructure services | ### Names of the infrastructure services | ||
### Service providers (responsible Service Owners) | ### Service providers (responsible [[Roles within ITIL V3#Service Owner|Service Owners]]) | ||
### References to Operational Level Agreements (OLAs) | ### References to [[Checklist SLA OLA UC|Operational Level Agreements (OLAs)]] | ||
### Required changes to OLAs, if existing OLAs are not sufficient for the service to be established | ### Required changes to OLAs, if existing OLAs are not sufficient for the service to be established | ||
## Externally supplied Supporting Services on which this service is based | ## Externally supplied Supporting Services on which this service is based | ||
Line 79: | Line 76: | ||
### Name of the supplier | ### Name of the supplier | ||
### Responsible Supplier Manager | ### Responsible Supplier Manager | ||
### References to Underpinning Contracts (UCs) | ### References to [[Checklist SLA OLA UC|Underpinning Contracts (UCs)]] | ||
### Required changes to UCs, if existing UCs do not support the introduction of the new service | ### Required changes to UCs, if existing UCs do not support the introduction of the new service | ||
# Details on technical changes required to build, test, deploy and operate the service | # Details on technical changes required to build, test, deploy and operate the service | ||
Line 106: | Line 103: | ||
## Rules for archiving and backup | ## Rules for archiving and backup | ||
<p> </p> | |||
==== Service Design Package - Part 4: Planning Information ==== | ==== Service Design Package - Part 4: Planning Information ==== | ||
This part sets an intended time frame for the service implementation and estimates the required resources; this information may be updated later by Change, Release or Project Management. | This part sets an intended time frame for the service implementation and estimates the required resources; this information may be updated later by [[Change Management|Change]], [[Release and Deployment Management|Release]] or [[Project Management - Transition Planning and Support|Project Management]]. | ||
# Preliminary [[Project Management - Transition Planning and Support#Service Transition Plan|Service Transition Plan]] | |||
# Preliminary Service Transition Plan | |||
## Major project phases and milestones | ## Major project phases and milestones | ||
## Intended time schedule | ## Intended time schedule | ||
Line 119: | Line 115: | ||
# Required budget for service implementation (itemized) | # Required budget for service implementation (itemized) | ||
<p> </p> | |||
<!-- This page is assigned to the following categories: --> | <!-- This page is assigned to the following categories: --> |
Revision as of 09:39, 9 September 2011
<seo metakeywords="service design package, itil service design package, service design package template, itil sdp" metadescription="The Service Design Package (SDP) builds upon the Service Level Requirements. It further specifies the requirements from the viewpoint of the ..." />
ITIL Process: ITIL V3 Service Design - Service Level Management
Checklist Category: Checklists ITIL V3 Service Design
Source: Checklist "Service Design Package - SDP" from the ITIL Process Map V3
The Service Design Package (SDP) builds upon the Service Level Requirements. It further specifies the requirements from the viewpoint of the client and defines how these are actually fulfilled from a technical and organizational point of view. It is assumed that a bundle of Supporting Services is combined in order to deliver a Business Service for the client. In this context, the IT organization may opt to supply the Supporting Service with its own resources, or to use an external service supplier.
The Service Design Package is passed from Service Design to the Service Transition process and details all information required in order to develop the service solution, including a preliminary (intended) time-schedule for the Service Transition phase.
The Service Design Package contains the following information (the actual level of detail will vary, depending on the type of service):
Service Design Package - Part 1: Header
- Name of the service
- Clearance information (with location and date)
- Clearance of the Service Design Manager
- Clearance of the Service Design Package by Service Management (confirmation that the requirements as laid out in this document are able to be fulfilled and where necessary, specification of any preconditions which must be fulfilled before the service can go operational)
Service Design Package - Part 2: Detailed Requirements Specification as a Basis for Service Transition
This part builds upon the Service Level Requirements and specifies in more detail what conditions the new service and its underlying applications and infrastructure must fulfill, providing all information which is needed for building the new service.
- Service level requirements (reference to the SLR document, where service level requirements are defined)
- Functional requirements (the SLR document contains a summary description of the desired customer outcome; however, functional requirements may need to be specified in greater detail, especially if new applications/ systems are to be developed)
- Information security requirements which are relevant for the service
- Compliance requirements which are relevant for the service
- Architectural constraints (e.g. specific technology or vendors)
- Interface requirements (e.g. if a new system needs to communicate with other systems)
- Migration requirements (e.g. if data are to be migrated from an existing to a new application)
- Operational requirements (e.g. requirements for backup and restore mechanisms, compatibility with existing system monitoring tools)
- Required access rights (which users or user groups will require access to the service, and what levels of access must be provided)
Service Design Package - Part 3: Technical and Organizational Implementation Blueprint
This part details what must be done during Service Transition to meet the specified requirements.
- Transition strategy (a brief outline of the selected approach to implementing the new service)
- Testing strategy
- Deployment strategy
- Migration concept
- Back-out strategy in the case of a failed deployment
- Decomposition of the Business Service into Infrastructure Services
- Internal Infrastructure Services on which this service is based
- Names of the infrastructure services
- Service providers (responsible Service Owners)
- References to Operational Level Agreements (OLAs)
- Required changes to OLAs, if existing OLAs are not sufficient for the service to be established
- Externally supplied Supporting Services on which this service is based
- Names of the external services
- Name of the supplier
- Responsible Supplier Manager
- References to Underpinning Contracts (UCs)
- Required changes to UCs, if existing UCs do not support the introduction of the new service
- Internal Infrastructure Services on which this service is based
- Details on technical changes required to build, test, deploy and operate the service
- Development/ customization of base applications for the service (e.g. if the service to be introduced is based on the SAP system or a custom application)
- Supporting tools
- Development/ customization of migration tools
- Development/ customization of testing tools
- Development/ customization of deployment tools
- Development/ customization of back-out tools in the case of a failed release deployment
- Infrastructure modifications required to build, test, deploy and operate the service
- Infrastructure components to be purchased and installed
- Infrastructure components to be (re-)configured
- Required changes to facilities
- Organizational changes required to implement and operate the service
- Personnel resources to be added
- Specification of required resources
- Strategy for acquiring the resources
- Skills to be developed
- Specification of the required skills
- Strategy for acquiring the skills
- Changes to processes
- List of IT processes which must be changed or created, including process owners
- Detailed specification of required changes to IT processes, e.g. in the form of process designs
- Personnel resources to be added
- Operational concept, e.g.
- Routine administrative tasks to be carried out
- Rules for archiving and backup
Service Design Package - Part 4: Planning Information
This part sets an intended time frame for the service implementation and estimates the required resources; this information may be updated later by Change, Release or Project Management.
- Preliminary Service Transition Plan
- Major project phases and milestones
- Intended time schedule
- Required staff resources
- Required budget for service implementation (itemized)