== <span id="RFC ITIL">Overview</span> ==


'''ITIL Process''': [[ITIL V3 Service Transition|ITIL 2011 Service Transition]] - [[Change Management]]
'''ITIL Process''': [[ITIL V3 Service Transition|ITIL 2011 Service Transition]] - [[Change Management]]
Line 25: Line 27:


<p>&nbsp;</p>
<p>&nbsp;</p>
__TOC__
== Request for Change (RFC) - Contents ==


'''A Request for Change contains the following information:'''
''A Request for Change contains the following information:''


<p>&nbsp;</p>
<p>&nbsp;</p>


# Unique ID
===== Unique ID =====
# Date of submission
 
# Change Owner
===== Date of submission =====
# Initiator of the RFC (if not identical with Change Owner)
 
# Proposed Change priority (e.g. "Very High (Emergency Change)", "High", "Normal", "Low" - may be overruled by Change Management during Change assessment)
===== Change Owner =====
# Reference to Change Proposal (if the Change is related to a Change Proposal submitted at an earlier stage)
 
# Description of the Change being applied for
===== Initiator of the RFC =====
## Summary description
(if not identical with Change Owner)
## Business case
 
### Reason for the Change to be implemented
===== Proposed Change priority =====
### Costs
(e.g. "Very High (Emergency Change)", "High", "Normal", "Low" - may be overruled by Change Management during Change assessment)
### Benefits
 
### Consequences if the Change is not implemented
===== Reference to Change Proposal =====
### References (e.g. to a [[Problem Management#Problem Record|Problem Record]] triggering this RFC)
(if the Change is related to a Change Proposal submitted at an earlier stage)
## Business areas on the client-side affected by the Change
 
## Services affected by the Change
===== Description of the Change being applied for =====
## IT infrastructure components ([[Checklist CMS CMDB|CIs]]) affected by the Change
# Summary description
## Technology aspects (is a new technology being introduced?)
# Business case
# Risks during the implementation of the Change  
## Reason for the Change to be implemented
## Identified risks
## Costs
## Counter-measures (e.g. reversion procedure)
## Benefits
## Back-out strategy for the case of a failed Change implementation
## Consequences if the Change is not implemented
# Predicted/suggested time schedule for the implementation
## References (e.g. to a [[Problem Management#Problem Record|Problem Record]] triggering this RFC)
# Estimate of resources for the implementation
# Business areas on the client-side affected by the Change
## Required personnel resources (from which areas?)
# Services affected by the Change
## Estimated work effort for the required personnel resources
# IT infrastructure components ([[Checklist CMS CMDB|CIs]]) affected by the Change
## Cost estimate (itemized for bigger Changes)
# Technology aspects (is a new technology being introduced?)
# Statement as to whether a budget is allocated and cleared for this Change
 
# If applicable, index of additional supporting documents (e.g. the [[Service Level Management#SDP|Service Design Package]] for major additions or modifications to services)
===== Risks =====
# Approval or rejection
(Risks during the implementation of the Change)
## Date
# Identified risks
## Person/ body in charge of the approval ([[Roles within ITIL V3#Change Manager|Change Manager]]/ [[Roles within ITIL V3#Change Advisory Board (CAB)|CAB]]/ [[Roles within ITIL V3#Emergency Change Advisory Board (ECAB)|ECAB]])
# Counter-measures (e.g. reversion procedure)
## Change reviewers
# Back-out strategy for the case of a failed Change implementation
## Priority assigned by Change Management
 
## Restrictions
===== Time schedule =====
## If applicable, reasons for rejecting the RFC
(Predicted/suggested time schedule for the implementation)
 
===== Estimate of resources for the implementation =====
# Required personnel resources (from which areas?)
# Estimated work effort for the required personnel resources
# Cost estimate (itemized for bigger Changes)
 
===== Budget =====
(Statement as to whether a budget is allocated and cleared for this Change)
 
===== Additional supporting documents =====
(If applicable, index of additional supporting documents, e.g. the [[Service Level Management#SDP|Service Design Package]] for major additions or modifications to services)
 
===== Approval or rejection =====
# Date
# Person/ body in charge of the approval ([[Roles within ITIL V3#Change Manager|Change Manager]]/ [[Roles within ITIL V3#Change Advisory Board (CAB)|CAB]]/ [[Roles within ITIL V3#Emergency Change Advisory Board (ECAB)|ECAB]])
# Change reviewers
# Priority assigned by Change Management
# Restrictions
# If applicable, reasons for rejecting the RFC


<p>&nbsp;</p>
<p>&nbsp;</p>

Revision as of 16:40, 22 April 2012

<seo metakeywords="request for change process, itil rfc process, change request checklist" metadescription="The Request for Change (RFC) is formal request for the implementation of a Change. A Request for Change is to be submitted to Change Management ..." />

DE - ES - Checklist Request for Change RFC - Template Request for Change RFCdiese Seite auf Deutschesta página en español
DE - ES - Checklist Request for Change RFC - Template Request for Change RFC


Overview

ITIL Process: ITIL 2011 Service Transition - Change Management

Checklist Category: Checklists ITIL Service Transition

Source: Checklist "Request for Change - RFC" from the ITIL Process Map

 

The Request for Change (RFC) is formal request for the implementation of a Change. A Request for Change is to be submitted to Change Management for any non-standard Change (a set of standard/ routine Changes is usually defined by Change Management; these are minor Changes which do not require submission to the Change Management process).

A Change is backed by a Change Owner, holding a budget for its implementation. In many cases the Change Owner is identical with the RFC initiator. Typically Changes are owned by Service Management roles (e.g. the Problem Manager or Capacity Manager) or by IT management.

The RFC is a precursor to the Change Record and contains all information required to approve a Change. Further information is added as the Change progresses through its lifecycle.

The level of detail depends on the size and likely impact of the Change. Often there will be references to further documents containing more detailed information, e.g. a detailed Change proposal. As major Changes are typically implemented as projects, the RFC often takes on the role of what is also known as a "Project Charter".

 

Request for Change (RFC) - Contents

A Request for Change contains the following information:

 

Unique ID
Date of submission
Change Owner
Initiator of the RFC

(if not identical with Change Owner)

Proposed Change priority

(e.g. "Very High (Emergency Change)", "High", "Normal", "Low" - may be overruled by Change Management during Change assessment)

Reference to Change Proposal

(if the Change is related to a Change Proposal submitted at an earlier stage)

Description of the Change being applied for
  1. Summary description
  2. Business case
    1. Reason for the Change to be implemented
    2. Costs
    3. Benefits
    4. Consequences if the Change is not implemented
    5. References (e.g. to a Problem Record triggering this RFC)
  3. Business areas on the client-side affected by the Change
  4. Services affected by the Change
  5. IT infrastructure components (CIs) affected by the Change
  6. Technology aspects (is a new technology being introduced?)
Risks

(Risks during the implementation of the Change)

  1. Identified risks
  2. Counter-measures (e.g. reversion procedure)
  3. Back-out strategy for the case of a failed Change implementation
Time schedule

(Predicted/suggested time schedule for the implementation)

Estimate of resources for the implementation
  1. Required personnel resources (from which areas?)
  2. Estimated work effort for the required personnel resources
  3. Cost estimate (itemized for bigger Changes)
Budget

(Statement as to whether a budget is allocated and cleared for this Change)

Additional supporting documents

(If applicable, index of additional supporting documents, e.g. the Service Design Package for major additions or modifications to services)

Approval or rejection
  1. Date
  2. Person/ body in charge of the approval (Change Manager/ CAB/ ECAB)
  3. Change reviewers
  4. Priority assigned by Change Management
  5. Restrictions
  6. If applicable, reasons for rejecting the RFC